Additional time OK'd for shipment of Vermont Yankee waste

(WCAX)
Published: Mar. 3, 2020 at 1:31 PM EST
Email this link
Share on Pinterest
Share on LinkedIn

Federal regulators have approved a relaxed timetable for the Vermont Yankee nuclear power plant to ship low-level radioactive waste.

The Brattleboro Reformer reported Monday that NorthStar Nuclear Decommissioning Co. requested an exemption from the Nuclear Regulatory Commission's requirement that waste be shipped to a Texas disposal facility in 20 days. NorthStar has encountered weekslong delays shipping waste to the facility. NorthStar CEO Scott State wrote an email Monday asking that federal regulators understand that the "twenty-day notification standard" is not workable in every situation.

Neil Sheehan, a spokesman for the NRC, wrote an email that a 45-day window will be allowed.